Open cell: DVU®10 has open cell greater than 90%, while installation with shredder "COP5" has open cell greater than 80%.
Initial Investment: With the DVU®10 savings in the installation would be R$ 840.000,00, or 11% cheaper than the option with shredder "COP5".
Energy consumption: With the DVU®10 the energy consumption will be greater 4225,00 MW/h harvest, or 18.5% greater than option with shredder "COP5". *¹ In Reals this difference would be R$ 591,494.00. *¹ Remark that DVU®10 makes possible an open cell greater than 90% while the "COP5" makes possible only greater than 80%. Better compare to the DVU®5, which has open cell greater than 85% and expected energy consumption would be the same as the installation with shredder "COP5".
Maintenance: With the DVU®10 savings on maintenance would be R$ 82,000,00.
Total: With the DVU®10 savings would be R$331.000,00. With the DVU®5 savings would be R$922.500,00.